# HVAC 500kV 110Bus

## Description

The **110-Bus 500 kV Transmission System** example, located in **File > Open an Example File > Benchmarks**, simulates a 500 kV, 110-bus transmission network operating at 60 Hz with 14 hydraulic generation turbine plants (synchronous machines with regulators).

The objective is to study system behavior under single-line-to-ground, two-phase-to-ground, and three-phase faults, as well as electromagnetic transients caused by machine or line outages. The model enables analysis of instability, islanding, and resonance phenomena. This configuration includes two three-phase faults on Buses 7 and 9; fault times are user-configurable, and additional faults can be added at other buses.

<figure><img src="https://3623212549-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLxgTpoh7kyPmQ5vuyqD7%2Fuploads%2Fgit-blob-cbbfe1785ce33780fb8b3ab69ab89dbe0b4988bf%2Fimage%20(1363).png?alt=media" alt=""><figcaption></figcaption></figure>

## Requirements

This example model does not require any additional hardware or licenses.

## Detailed explanation

All generator units are equipped with internal exciters, governors (speed regulators), and stabilizers. To modify these settings, double-click the machine subsystem and edit the parameters in the mask.

<figure><img src="https://3623212549-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLxgTpoh7kyPmQ5vuyqD7%2Fuploads%2Fgit-blob-de83e8352c05a5c635dfc07663328ede5a880046%2Fimage%20(1364).png?alt=media" alt=""><figcaption><p>Synchronous machine configuration settings</p></figcaption></figure>

Fault configuration:

* Three-phase fault at Bus 7: T1 = 10.1 s, duration = 0.01 s.
* Three-phase fault at Bus 9: T1 = 0.1 s, duration = 0.05 s.

By default, both faults are enabled. Use the Enable option within the fault subsystems named Flt1\_B7 and Flt\_B9 to turn each fault on or off. To change activation and clearing times, edit parameters T1 and T2 inside each fault subsystem.

<figure><img src="https://3623212549-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLxgTpoh7kyPmQ5vuyqD7%2Fuploads%2Fgit-blob-970d972fd9dc208d0ad5abecc8bf4815442c277e%2Fimage%20(1365).png?alt=media" alt=""><figcaption><p>Fault configuration settings</p></figcaption></figure>

The default ScopeView template captures 1 s of data. As a result, the Bus 7 fault at 10.1 s will not appear unless you increase the capture time in ScopeView or adjust T1/T2 for the Bus 7 fault.

## Simulation and results

Running the provided scenario produces the following observations for a three-phase-to-ground fault at Bus 9:

<figure><img src="https://3623212549-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLxgTpoh7kyPmQ5vuyqD7%2Fuploads%2Fgit-blob-1afc9b0b7c612e3a10ec2b050cc421340ab768c3%2Fimage%20(1366).png?alt=media" alt=""><figcaption><p>Voltage of Buses 7 and 9 with a three-phase to ground fault at Bus 9.</p></figcaption></figure>

<figure><img src="https://3623212549-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLxgTpoh7kyPmQ5vuyqD7%2Fuploads%2Fgit-blob-589f6572b49292dc6e0cf0db7552f5c19e7e5453%2Fimage%20(1367).png?alt=media" alt=""><figcaption><p>Voltage of Bus and Fault current with a three-phase to ground fault at Bus 9</p></figcaption></figure>

<figure><img src="https://3623212549-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLxgTpoh7kyPmQ5vuyqD7%2Fuploads%2Fgit-blob-a2fbdd3c4fa4544f5388404dd8fc717b43491634%2Fimage%20(1368).png?alt=media" alt=""><figcaption><p>Machine speed and voltages with a three-phase to-ground fault at Bus 9</p></figcaption></figure>

For real-time performance, see [Benchmarks | 110-Bus 500 kV Transmission System](https://www.opal-rt.com/docs/hypersim/overview/performance-benchmarks/110-bus-500-kv-transmission-system.md)


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://www.opal-rt.com/docs/hypersim/examples/benchmarks/hvac-500kv-110bus.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.