> For the complete documentation index, see [llms.txt](https://www.opal-rt.com/docs/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://www.opal-rt.com/docs/op1400pr/get-started/perform-a-site-acceptance-test-sat.md).

# Perform a Site Acceptance Test (SAT)

This document provides the **standard Site Acceptance Test (SAT) procedure** for the **OP1400PR PHIL test bench**.

It **only covers the unparalleled independent operation in a three-phase 120 Vrms output configuration in voltage control mode**. However, there may be other output configurations and modes tested on site, depending on your specific test bench model and risk assessment done before the visit of the OPAL-RT field application engineer (FAE).

It is recommended to continue with this procedure only **after completing the test bench** [**assembly**](https://www.opal-rt.com/docs/op1400pr/get-started/assemble-the-test-bench.md) **and** [**connection**](https://www.opal-rt.com/docs/op1400pr/get-started/connect-the-test-bench.md) **of the test bench**, to **ensure proper functioning of all modules**.

{% hint style="danger" %}
Verify that the **mains supply is disconnected** and that **no external energy source is connected to the Output Interface, LP or HP Bus Bar boxes terminals** before opening the cabinet doors or protective covers.

Failure to do so could expose the user to risks of **electric shocks**. Refer to <mark style="background-color:$danger;">OP1400PR PHIL Prime Test Bench Series Important Safety Information</mark> for more information.
{% endhint %}

**SEE ALSO** [<mark style="background-color:$danger;">**Safety Warnings, Maintenance & Repair | Avertissements de sécurité, maintenance & réparation**</mark>](https://opal-rt.atlassian.net/wiki/spaces/PHDGD/pages/144718013)

## Validate the electrical wiring inside the cabinet <a href="#validating-the-electrical-wiring-inside-the-cabinet" id="validating-the-electrical-wiring-inside-the-cabinet"></a>

### Ground connections <a href="#ground-connections" id="ground-connections"></a>

Visually inspect **ground connections** of **all the modules**. They are accessible from the **rear of the cabinet**.

{% hint style="info" %}
Particular attention should be given to the **ground connections** of the **OP8110 amplifiers** and **DC power supplies** as they are **installed on site**.
{% endhint %}

{% columns %}
{% column width="66.66666666666666%" %}
With a **screwdriver** and a **compatible tip** or **socket**, validate that **all ground connections** are **properly tightened**.

Using a **multimeter**, perform a **continuity measurement** between the **test bench chassis** (any **bare-metal** part of a **module** or the cabinet) and the **building ground** (for example **metal conduit**, **junction box**, or **exposed ground wire**), to ensure that the measured resistance is **less than 1 ohm**.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FPAyty5R9d6rrEGoYnlz5%2Fimage.png?alt=media&amp;token=732476d8-a62b-4d19-9eb2-2216115e4081" alt="" width="162"><figcaption></figcaption></figure>
{% endcolumn %}

{% column width="33.33333333333334%" %}

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FQcP2LgbJi0irPU9pXCRX%2FMultim%C3%A8tre.png?alt=media&amp;token=fc11fcb1-36bf-4b07-8ebe-2589ea9d7730" alt=""><figcaption></figcaption></figure>

{% endcolumn %}
{% endcolumns %}

In the following sections we show the ground connections to test on each module, from the top to the bottom of the cabinet.

#### E-stop module <a href="#grounding-of-e-stop-module" id="grounding-of-e-stop-module"></a>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FiQRXzPT4df5AO3qUdWVQ%2F113-1311%20rev%201.0%20groud%20cable.png?alt=media&amp;token=485ec357-910f-4696-9033-233a5da69127" alt="" width="563"><figcaption><p>E-stop ground cable</p></figcaption></figure>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FCjGAkD5gyHDFWZEiQdBh%2Fimage.png?alt=media&amp;token=f1c31bda-5d97-45ef-852b-21450ad89480" alt=""><figcaption><p>E-stop module ground terminal</p></figcaption></figure>

#### Simulator

The model of simulator may vary depending on your order.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FULwIvrAHk68GMju22yap%2Fimage.png?alt=media&amp;token=c82bc70e-84bd-4651-b9a8-af2a8929f68d" alt=""><figcaption><p>OP4610XG2 simulator illustrated</p></figcaption></figure>

#### Output interface modules <a href="#grounding-of-output-interface-box" id="grounding-of-output-interface-box"></a>

Depending on your model, you may have **one** or **two output interface** modules.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FiQRXzPT4df5AO3qUdWVQ%2F113-1311%20rev%201.0%20groud%20cable.png?alt=media&amp;token=485ec357-910f-4696-9033-233a5da69127" alt="" width="563"><figcaption><p>Output interface ground wire</p></figcaption></figure>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FIT5DIedQ6gB1j4o66F18%2Fimage.png?alt=media&amp;token=22ce9aa0-e25a-4a93-ace4-673f88782a17" alt=""><figcaption><p>Output interface ground terminal</p></figcaption></figure>

#### LP and HP bus bar modules <a href="#grounding-of-lp-hp-bus-bar-boxes" id="grounding-of-lp-hp-bus-bar-boxes"></a>

The number and type of bus bar (LP or HP) modules depend on the test bench model and configuration ordered.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FiQRXzPT4df5AO3qUdWVQ%2F113-1311%20rev%201.0%20groud%20cable.png?alt=media&amp;token=485ec357-910f-4696-9033-233a5da69127" alt="" width="563"><figcaption><p>LP bus bar ground cable</p></figcaption></figure>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2F8HhKaaQ6o9hiayKCgbVE%2F113-1804%20rev%201.0%20ground%20cable.png?alt=media&amp;token=5dc35fb1-43d0-4cce-8b5c-ad1cdd77599e" alt="" width="563"><figcaption><p>HP bus bar ground cable</p></figcaption></figure>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2Fgqh2YRgrA91lOPpOAH9Z%2Fimage.png?alt=media&amp;token=1ed085a4-9569-4e4f-ab37-d7df4fcd65cc" alt=""><figcaption><p>LP/HP bus bar ground terminal</p></figcaption></figure>

#### OP8110 4Q power amplifier <a href="#grounding-of-pdu" id="grounding-of-pdu"></a>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FiQRXzPT4df5AO3qUdWVQ%2F113-1311%20rev%201.0%20groud%20cable.png?alt=media&amp;token=485ec357-910f-4696-9033-233a5da69127" alt="" width="563"><figcaption><p>OP8110 ground cable</p></figcaption></figure>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FfrPYwDsuVKulRKk4ydUy%2Fimage.png?alt=media&amp;token=43666dbd-49d1-4f64-af58-d4d4e2527d59" alt=""><figcaption><p>OP8110 amplifier ground terminal</p></figcaption></figure>

#### Power distribution unit (PDU) <a href="#grounding-of-pdu" id="grounding-of-pdu"></a>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2F8HhKaaQ6o9hiayKCgbVE%2F113-1804%20rev%201.0%20ground%20cable.png?alt=media&amp;token=5dc35fb1-43d0-4cce-8b5c-ad1cdd77599e" alt="" width="563"><figcaption><p>PDU ground cable</p></figcaption></figure>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FFljcnjbkChCq9uTwAPev%2Fimage.png?alt=media&amp;token=acee784d-70fa-4315-8994-63353c70eef9" alt=""><figcaption><p>PDU ground terminal</p></figcaption></figure>

### DC supplies power connections <a href="#dc-supplies-power-connections" id="dc-supplies-power-connections"></a>

For each **ITECH IT6000C DC power supply**, validate that

* **DC output cables** are properly installed:
  * **Black wire** to the **negative** terminal
  * <mark style="color:red;">**Red wire**</mark> to the **positive** terminal.

{% columns %}
{% column %}

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FJg41pNPOhGatFlZUXvgB%2Fimage.png?alt=media&amp;token=bc0d926a-b10d-4e78-af6e-ee28e82174bd" alt="" width="375"><figcaption><p>With protective cover</p></figcaption></figure>
{% endcolumn %}

{% column %}

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FEJrFCoGThUtWfk0jz1Hj%2Fimage.png?alt=media&amp;token=ec8334cf-a933-4dff-82a4-b4906d5b4ae3" alt=""><figcaption><p>Without protective cover</p></figcaption></figure>
{% endcolumn %}
{% endcolumns %}

* **AC input cables** are properly installed:
  * <mark style="color:$danger;">**Red**</mark>, **black**, and <mark style="color:blue;">**blue**</mark> wires are present and connected.
    * Verify that all wires are properly secured by gently pulling each wire by hand.
    * No movement should be observed.
  * <mark style="color:green;">**Green**</mark> and <mark style="color:$warning;">**yellow**</mark> wire is **securely fastened** on the **ground screw**.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FS57t6M0oeZFCjJZtUjB3%2Fimage.png?alt=media&amp;token=c2d5ec1d-75f9-4854-a832-346fd6a2b0dd" alt="" width="563"><figcaption></figcaption></figure>

* On **OP1400PR-30** and **OP1400PR-60**:
  * Validate that line wires on the **3 DC power supplies** are **interleaved** such as in the image below (actual wire colors may vary from the image).

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FZnSd3VnX8sJQxThjS67A%2Fimage.png?alt=media&amp;token=f3f250df-b539-490f-b821-eacb18dca01c" alt="" width="563"><figcaption></figcaption></figure>

### OP8110 amplifier connections <a href="#op8110-amplifier-connections" id="op8110-amplifier-connections"></a>

#### Optical synchronization cables <a href="#optical-synchronization-cables" id="optical-synchronization-cables"></a>

{% hint style="info" %}
**This applies to models OP1400PR-30 and OP1400PR-60 only.**

OP1400PR-10 and OP1400PR-20 has only one OP8110 amplifier and therefore have no synchronization cable.
{% endhint %}

Validate that the **optical synchronization cables** are **present** and are **installed properly in the following way**.

{% tabs %}
{% tab title="OP1400PR-30" %}

* The synchronization cable from the **Tx connector** of the **top unit** is connected to the **Rx connector** of the **bottom unit.**

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FJZOeAcG9MbwTUoJt41X4%2FOP1400PR-30%20synchronization.png?alt=media&amp;token=0bcff591-a318-44cf-b381-c593636d8798" alt=""><figcaption></figcaption></figure>
{% endtab %}

{% tab title="OP1400PR-60" %}

* The synchronization cable from the **Tx connector** of the **top unit** is connected to the **Rx connector** of the **middle unit.**
* The synchronization cable from the **Tx connector** or the **middle unit** is connected to the **Rx connector** of the **bottom unit.**

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FBWmft09BbV4rcVT7ECVX%2FOP1400PR-60%20synchronization.png?alt=media&amp;token=846765e6-c796-406f-b718-2ad705a1180a" alt=""><figcaption></figcaption></figure>
{% endtab %}
{% endtabs %}

#### Auxiliary supply port <a href="#auxiliary-supply" id="auxiliary-supply"></a>

**Visually check** that **every amplifier group** has its **auxiliary supply cable(s)** inserted into the associated ports shown in the images below.

**Verify by hand** that the connectors are **properly tightened**.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FOJL3J78mc3zf1fLEtUC5%2Fimage.png?alt=media&amp;token=080f7f23-59e0-4803-b0da-bfe12f99fdc8" alt=""><figcaption><p>OP8110-3 auxiliary supply connection</p></figcaption></figure>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2F6gMhqpHyAdZHM804HQbv%2Fimage.png?alt=media&amp;token=65718e9d-b1cb-4aa0-adb4-6875928f3602" alt=""><figcaption><p>OP8110-6 auxiliary supply connection</p></figcaption></figure>

#### High-voltage DC supply <a href="#high-voltage-dc-supply" id="high-voltage-dc-supply"></a>

Validate that the **DC inputs** of **each amplifier group** are connected correctly.

For model **OP1400PR-60**, be sure that all **jumper cables** are present and correctly connected. Refer to the **illustrations below**.

{% hint style="danger" %}
**Ensure the polarity is correct** when connecting the banana plugs: **red banana plug in red terminal and black banana plug in black terminal**.
{% endhint %}

{% tabs %}
{% tab title="OP1400PR-10" %}

* One pair of banana plugs is connected to the connectors **DC1**

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FCfu7bWIBkw0fBOhDudWr%2Fimage.png?alt=media&amp;token=510fe0cb-a974-4f4e-984a-88c027fcc573" alt=""><figcaption></figcaption></figure>
{% endtab %}

{% tab title="OP1400PR-20" %}

* One pair of banana plugs is connected to the connectors **DC1**
* One pair of banana plugs is connected to the connectors **DC2**

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2Fz4nPiRdpJzfBVzWB8847%2Fimage.png?alt=media&amp;token=d49f042b-2e5a-4542-a48f-9db794dadcb5" alt=""><figcaption></figcaption></figure>
{% endtab %}

{% tab title="OP1400PR-30" %}

* One pair of banana plugs is connected to connectors **DC1** of the **OP8110-6** (**top most** amplifier)
* One pair of banana plugs is connected to connectors **DC2** of the **OP8110-6** (**top most** amplifier)
* One pair of banana plugs is connected to connectors **DC1** of the **OP8110-3** (**bottom most** amplifier)

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FesbshhXzbhCkKmMyaKYy%2Fimage.png?alt=media&amp;token=9e21e7cf-5ac2-4b5a-a5fc-d5546f90c303" alt=""><figcaption></figcaption></figure>
{% endtab %}

{% tab title="OP1400PR-60" %}

* One pair of banana plugs to the **DC1** connectors of the top most **OP8110-6** amplifier.
* **Red jumper cable** (T00-9659) **from the DC1 to the DC2 connector** of the same amplifier.
* **Black jumper cable** (T00-9658) **from the DC1 to the DC2** connector of the same amplifier.
* **Repeat the same steps** for the two other amplifiers.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FH9664scTSvwpdEcg0VU8%2Fimage.png?alt=media&amp;token=ae7a0991-f2a6-4715-afbf-79c4c98208fa" alt=""><figcaption></figcaption></figure>
{% endtab %}
{% endtabs %}

### Signal and control harnesses <a href="#signal-and-control-harnesses" id="signal-and-control-harnesses"></a>

**Signal and control harnesses** (connected between modules within the test bench) are installed and secured at the **OPAL-RT factory** before shipping and **should not require any manipulation by the user**.

However, it is recommended to **visually inspect** the **inside of the test bench** to ensure that **there are no free-hanging harness connectors**. If there happens to be some, please contact your [**local OPAL-RT representative**](https://www.opal-rt.com/contact-us/) or [**OPAL-RT support team**](https://www.opal-rt.com/support/) so we can assist you in correctly reconnecting them appropriately.

#### E-stop P1 connector to  PDU P1 connector <a href="#connection-from-the-p1-connector-of-the-e-stop-module-to-the-p1-connector-of-the-pdu" id="connection-from-the-p1-connector-of-the-e-stop-module-to-the-p1-connector-of-the-pdu"></a>

{% hint style="warning" %}
For **detailed pinout information**, refer to the **section** named "**Terminal Block Pinout (TBP)**" in the “**Connections and Signals Overview**” **document** on the **USB key** supplied with your system.
{% endhint %}

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FIYoPp13UPmzo1rK3tHPZ%2Fimage.png?alt=media&amp;token=d94fa2d4-9aad-4805-94db-5d83db1c8926" alt=""><figcaption></figcaption></figure>

#### E-stop P2 connector to LP/HP bus bar module P1 connector <a href="#connection-from-the-p1-connector-of-the-e-stop-module-to-the-p2-connector-of-the-lp-hp-bus-bar-boxes" id="connection-from-the-p1-connector-of-the-e-stop-module-to-the-p2-connector-of-the-lp-hp-bus-bar-boxes"></a>

{% hint style="warning" %}
For **detailed pinout information**, refer to the **section** named "**Terminal Block Pinout (TBP)**" in the “**Connections and Signals Overview**” **document** on the **USB key** supplied with your system.
{% endhint %}

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FPjKgUaEzNB8rWBL0x90x%2Fimage.png?alt=media&amp;token=b5b95210-7153-4971-bcc5-c0f9b892ebbd" alt=""><figcaption></figcaption></figure>

#### SFP cables from simulator to amplifiers <a href="#validating-the-control-equipment" id="validating-the-control-equipment"></a>

The SFP cables were [connected by the user](https://www.opal-rt.com/docs/op1400pr/get-started/connect-the-test-bench.md#cable-routing).

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FbNDTXkw1C2tA5u0AbFdQ%2Fimage.png?alt=media&amp;token=e282c7e9-a3d0-4102-9595-70dc43f497cc" alt="" width="340"><figcaption></figcaption></figure>

## Validate the control equipment <a href="#validating-the-control-equipment" id="validating-the-control-equipment"></a>

Please refer to the section [Operate the test bench](https://www.opal-rt.com/docs/op1400pr/operate-the-test-bench/operate-the-test-bench.md) of this manual if unexpected results are obtained.

### Power supply to the control equipment <a href="#supplying-the-control-equipment" id="supplying-the-control-equipment"></a>

{% columns %}
{% column %}
The OP1400PR test benches are assembled with two **universal 100-240 Vac power** **bars** labeled **#1** and **#2**. They **supply the various control equipment** in the test bench. The **power cables** are **routed** toward the **bottom of the cabinet**.

Ensure that **each power bar is plugged** into a proper **electrical outlet**.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FmH5d2rl3PJ8icYM2fGLS%2Fimage.png?alt=media&amp;token=9577edb0-85ce-43d0-a34b-fb4172c87eb4" alt=""><figcaption><p>Power bars and supply cable routing toward the bottom</p></figcaption></figure>
{% endcolumn %}

{% column %}

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FfRp4buFbsptMG1h6t606%2Fimage.png?alt=media&amp;token=be0dbb33-2e9b-4b95-848d-846f06c1a7c5" alt=""><figcaption><p>Cabinet (rear view)</p></figcaption></figure>
{% endcolumn %}
{% endcolumns %}

{% columns %}
{% column %}
**Turn the power switch to the ON** (I) position and validate that the **light** on the power bar **turns on**.

{% endcolumn %}

{% column %}

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FFv3RmZgyRMtae7HgJM9s%2Fimage.png?alt=media&amp;token=284adca7-c9e0-4ecf-8be8-d07b5db9a46a" alt=""><figcaption><p>Power bar on/off switch and breaker reset</p></figcaption></figure>
{% endcolumn %}
{% endcolumns %}

### PDU 24 V control power <a href="#validating-the-pdu" id="validating-the-pdu"></a>

The [**PDU**](https://www.opal-rt.com/docs/op1400pr/op1400pr-overview/description-and-components/power-distribution-unit-pdu.md) provides **24 V control power** for various modules and **12 V auxiliary power** for **amplifier control circuits**. When the power bars are turned ON, the “**24 V ON**” **LED** light will turn **ON**.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FGJepzNObbwXpMXxza787%2Fimage.png?alt=media&amp;token=ef3bbfff-c549-42c0-944d-ea88f5cee78b" alt="" width="392"><figcaption></figcaption></figure>

### E-stop module 24 V control power <a href="#validating-the-e-stop-module" id="validating-the-e-stop-module"></a>

When the power bars are turned ON, the [**E-stop module**](https://www.opal-rt.com/docs/op1400pr/op1400pr-overview/description-and-components/emergency-stop-module.md) “**24V ON**” **LED** light will turn **ON**.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FrXi4px1902YptxkHlLfn%2Fimage.png?alt=media&amp;token=b3d81086-1424-4926-96b9-5013fb8f7956" alt=""><figcaption></figcaption></figure>

### Start/Stop buttons <a href="#validating-the-start-stop-buttons" id="validating-the-start-stop-buttons"></a>

Ensure the E-stop (emergency stop) button on the [**E-stop module**](https://www.opal-rt.com/docs/op1400pr/op1400pr-overview/description-and-components/emergency-stop-module.md) is in the **released position** (not pressed) . If it's pressed in, **rotate it clockwise to release it**.

{% columns %}
{% column width="75%" %}

1. Press the **START** button on the **E-stop module** to activate the **PDU main contactor** that supplies the ITECH DC power supplies:
   1. The **light** on the **Start/Stop** **buttons** should **turn ON**.
   2. The **PDU main power contactor** should **close** with an **audible sound**.
2. Press the **STOP button**:
   1. The **light** on the **Start/Stop buttons** should turn **OFF**.
   2. The **PDU main power contactor** should **open** with an **audible sound**.
      {% endcolumn %}

{% column width="25%" %}

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FxpKltAmjkSIPxZlyGjFU%2Fimage.png?alt=media&amp;token=ab8664e4-2880-49db-a1c1-68e7eb5b9e23" alt=""><figcaption></figcaption></figure>
{% endcolumn %}
{% endcolumns %}

### Emergency stop button <a href="#validating-the-emergency-stop-button" id="validating-the-emergency-stop-button"></a>

Ensure the E-stop (emergency stop) button on the [**E-stop module**](https://www.opal-rt.com/docs/op1400pr/op1400pr-overview/description-and-components/emergency-stop-module.md) is in the **released position** (not pressed) . If it's pressed in, **rotate it clockwise to release it**.

{% columns %}
{% column width="75%" %}

1. Press the Start button on the E-stop module to activate the PDU main contactor that supplies the ITECH DC power supplies:
   1. The **light** on the **Start/Stop** buttons should **turn ON**.
   2. The **PDU main power contactor** should **close** with an **audible sound**.
2. **Press the emergency stop button**:
   1. The light on the **Start/Stop buttons** should **turn OFF**.
   2. The “**24V ON**” **LEDs** on the [**LP bus bar module**](https://www.opal-rt.com/docs/op1400pr/op1400pr-overview/description-and-components/lp-bus-bar-module.md) and [**HP bus bar module**](https://www.opal-rt.com/docs/op1400pr/op1400pr-overview/description-and-components/hp-bus-bar-modules.md) (if present) should **turn OFF**.
   3. The **PDU main power contactor** should **open** with an **audible sound**.
   4. **Release the E-stop** by **rotating** it **clockwise**.
      {% endcolumn %}

{% column width="25%" %}

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FOCMyPr8MRK3ny5UCFzL7%2Fimage.png?alt=media&amp;token=4103cfae-48bd-4eb0-b093-c675be418f88" alt=""><figcaption></figcaption></figure>
{% endcolumn %}
{% endcolumns %}

### Bus bars <a href="#validating-the-bus-bars" id="validating-the-bus-bars"></a>

* Ensure that:&#x20;
  * The **100-240 VAC power bars** of the test bench are **turned on**.
  * The **100-240 VAC entry module** of the PDU is **switched on**.
* Then, make sure the **E-stop  button is in the released** position.
  * If it's pressed in, rotate it clockwise to release it.
* Validate that the “**24V ON**” **LED**s on the [LP bus bar](https://www.opal-rt.com/docs/op1400pr/op1400pr-overview/description-and-components/lp-bus-bar-module.md) and the [HP bus bar](https://www.opal-rt.com/docs/op1400pr/op1400pr-overview/description-and-components/hp-bus-bar-modules.md) (if present) are **on**.
* Validate the **DUT Enable** **button** for **each DUT**:
  * **Press the&#x20;**<mark style="color:$success;">**Start**</mark>**&#x20;button**: The **light** located between the Start and Stop buttons should start **blinking**.
  * **Press the&#x20;**<mark style="color:$danger;">**Stop**</mark>**&#x20;button**: The light located between the Start and Stop buttons should **turn off**.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2Fuf8XJc3xbXOVIQy4wXfG%2Fimage.png?alt=media&amp;token=5e0a6c66-78da-4735-b2f4-bb53e5e85066" alt=""><figcaption><p>LP bus bar (all models)</p></figcaption></figure>

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2F9jFj4lvdmMeAJHPgzA3e%2Fimage.png?alt=media&amp;token=fb674148-239e-463e-a0ec-13fd48ec94ca" alt=""><figcaption><p>HP bus bar (OP1400PR-30 and OP1400-60)</p></figcaption></figure>

### OP8110 units <a href="#validating-the-op8110-units" id="validating-the-op8110-units"></a>

With the 100–240 VAC entry module of the PDU still switched on, verify that every OP8110 unit is properly supplied by **pressing the ON/OFF button** and validating that **the button turns to&#x20;**<mark style="color:green;">**green**</mark>.

<figure><img src="https://3155739458-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FzVJdfp93TWLISP6nkqTs%2Fuploads%2FvqiSXMdU8dmnWme5aEFG%2Fimage.png?alt=media&amp;token=7468d620-5ced-4cbb-8320-aac972bb4b8b" alt=""><figcaption></figcaption></figure>

The functionality of the OP8110s' power circuits will be validated later in this document.

### Other control equipment (simulators, etc.) <a href="#validating-other-control-equipment-simulators-etc" id="validating-other-control-equipment-simulators-etc"></a>

For all **other control equipment**, please **refer** to their **specific user documentation**.

## Validate the high-voltage circuits <a href="#validating-the-high-voltage-circuits" id="validating-the-high-voltage-circuits"></a>

Please refer to section [**Operate the test bench**](https://www.opal-rt.com/docs/op1400pr/operate-the-test-bench/control-and-monitor-the-test-bench.md) for the details on how to prepare and operate the OP1400PR test benches.

Please refer to the [**Troubleshooting section**](https://www.opal-rt.com/docs/op1400pr/operate-the-test-bench/troubleshoot-the-test-bench.md) of this documentation if unexpected results are observed.

{% hint style="danger" %}
**Hazardous voltage levels will be present inside the cabinet during the execution of these tests**.\
Ensure all safety guidelines described in the <mark style="background-color:$danger;">**Safety Information**</mark> section are followed.

Failure to do so **could expose the user to risks of electric shocks**.
{% endhint %}

### Material requirements <a href="#material-requirements" id="material-requirements"></a>

The following material must be **provided by the customer** to validate the high-voltage circuitry of the OP1400PR test bench:

* **A three-phase resistive load**
  * The resistance and power rating of the load depend on the test bench model.\
    However, just for validation purposes, a **load between 100 and 200 ohms**, with a **power rating of 500 W** (the power rating depends on the output test voltage set during the test) would be sufficient.
* **A basic multimeter**

### OP1400PR test bench functional test procedure <a href="#op1400pr-bench-functional-test-procedure" id="op1400pr-bench-functional-test-procedure"></a>

{% stepper %}
{% step %}

#### Connect the OP8110 outputs

Connect the first OP8110 group (outputs L1, L2, and L3) to the **DUT1 inputs** of the **output interface** **or** the **LP/HP bus bar** (rear panel, inside the cabinet), using a three-phase **120 Vac topology**.
{% endstep %}

{% step %}

#### Connect the load

**Connect** the **resistive load** to the **DUT1 output** of the **output interface** **or** the **LP/HP bus bar** (front panel).
{% endstep %}

{% step %}

#### Power on the three-phase mains

{% endstep %}

{% step %}

#### Power on the ITECH DC power supplies

**Power on** the **ITECH DC power supplies** by&#x20;

* **Switching on** the **PDU** (front panel switch)
* **Pressing** the **start button** on the **E-stop module**.

**Set** the **ITECH DC power supply**:

* Output voltage: **500 V**
* Current to **±15 A**
* Power to **±6kW**

**Trigger on the output** of the ITECH DC power supply at this point.
{% endstep %}

{% step %}

#### Build and run the FAT model

Verify that the **provided FAT model** is set for:

* **Operating the OP8110** in **three-phase 120 Vrms**
* **Voltage mode control** for **group 1** (L1, L2, L3 outputs) of the **first OP8110 amplifier** of the test bench

**Build** and **run** the model in **RT-LAB** or **HYPERSIM** and **use** the **model UI**.

Once the model is running, **use the UI** to

* **Enable** the **DC bus**
* **Turn on** the **amplifier outputs**
* **Set the output voltage** to **120 Vrms**
  {% endstep %}

{% step %}

#### Validate voltage at DUT1 (before enabling)

**If connected directly to the output interface**

* Use a **multimeter** to **validate** that **each of the three-line-to-neutral voltages** is approximately **120 Vrms**

**If connected through the LP or HP bus bar modules**

* Press **Start** to **locally enable DUT1**
  * The **Enable** **button** should begin **blinking**.
* **Enable DUT1** **remotely** via **digital IOs** or **Ethernet**
  * The **Enable** **button** should turn **solid on** (not blinking)
  * The **internal contactors** should **close** with an **audible click**
* Use a multimeter to **validate** that **each of the three-line-to-neutral voltages** is approximately **120 Vrms**
* After the validation
  * **Disable DUT1** via **digital IOs** or **Ethernet**
  * Press the **Stop button** for **DUT1** on the **bus bar box**
    {% endstep %}

{% step %}

#### Shutdown

* From the **UI** of the re**al-time simulation model**
  * **Disable** the **OP8110 outputs**
  * **Reset** the **model**
  * **Trigger off** the **ITECH DC power supply output**
* **Switch off:**

  * The **PDU** (front panel switch)
  * The **three-phase mains**

  **Disconnect** the **load**<br>
  {% endstep %}

{% step %}

#### Repeat <mark style="background-color:$warning;">steps 1 to 5</mark> for DUT2 and DUT3

**Repeat&#x20;**<mark style="background-color:$warning;">**steps 1 to 5**</mark> using **DUT2** and then **DUT3 connection points** of the **output interface** or of the LP/HP bus bar modules.
{% endstep %}

{% step %}

#### <mark style="background-color:$warning;">Repeat steps 1 to 6 for all untested output of the OP8110</mark>

Repeat <mark style="background-color:$warning;">**steps 1 to 6**</mark> using the remaining untested output groups of OP8110 e.g.

* <mark style="background-color:$warning;">Outputs L4, L5, L6 of amplifier #1</mark>
* <mark style="background-color:$warning;">Outputs L1, L2, L3 of amplifier #2</mark>
* <mark style="background-color:$warning;">Outputs L4, L5, L6 of amplifier #2</mark>
* <mark style="background-color:$warning;">Etc.</mark>
  {% endstep %}
  {% endstepper %}


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://www.opal-rt.com/docs/op1400pr/get-started/perform-a-site-acceptance-test-sat.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.