> For the complete documentation index, see [llms.txt](https://www.opal-rt.com/docs/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://www.opal-rt.com/docs/smart-power-simulation-software-sps/get-started/per-unit-system-of-units.md).

# Per-Unit System of Units

## International System of Units

SPS Software uses the International System of Units (SI), as described in the following table.

| Quantity        | Unit                                       | Symbol     |
| --------------- | ------------------------------------------ | ---------- |
| Time            | second                                     | s          |
| Length          | meter                                      | m          |
| Mass            | kilogram                                   | kg         |
| Energy          | joule                                      | J          |
| Current         | ampere                                     | A          |
| Voltage         | volt                                       | V          |
| Active power    | watt                                       | W          |
| Apparent power  | volt-ampere                                | VA         |
| Reactive power  | var                                        | var        |
| Impedance       | ohm                                        | Ω          |
| Resistance      | ohm                                        | Ω          |
| Inductance      | henry                                      | H          |
| Capacitance     | farad                                      | F          |
| Flux linkage    | volt-second                                | V·s        |
| Rotation speed  | radians per second, revolutions per minute | rad/s, rpm |
| Torque          | newton-meter                               | N·m        |
| Inertia         | kilogram-meter^2                           | kg·m^2     |
| Friction factor | newton-meter-second                        | N·m·s      |

### What Is the Per-Unit System?

The per-unit system is widely used in the power system industry to express values of voltages, currents, powers, and impedances of various power equipment. It is mainly used for transformers and AC machines.

For a given quantity (voltage, current, power, impedance, torque, etc.) the per-unit value is the value related to a base quantity.

$$
base ,value, in , p.u=\frac{quantity , expressed , in , SI , units}{base , value}
$$

Generally the following two base values are chosen:

* The base power = nominal power of the equipment
* The base voltage = nominal voltage of the equipment

All other base quantities are derived from these two base quantities. Once the base power and the base voltage are chosen, the base current and the base impedance are determined by the natural laws of electrical circuits.

$$
base , current=\frac{base , power}{base , voltage} \\\[8pt]
base , impedance=\frac{base , voltage}{base , current }=\frac{(base , voltage)^2}{base , power }
$$

For a transformer with multiple windings, each having a different nominal voltage, the same base power is used for all windings (nominal power of the transformer). However, according to the above definitions, there are as many base values as windings for voltages, currents, and impedances.

The saturation characteristic of saturable transformer is given in the form of an instantaneous current versus instantaneous flux-linkage curve: i1 phi1; i2 phi2; … , in phin.

When the Per-Unit system is used to specify the transformer R L parameters, the flux linkage and current in the saturation characteristic must be also specified in pu. The corresponding base values are:

$$
base , instantaneous , current=(base , rms , current) \times \sqrt{2} \\\[8pt]
base , flux ,linkage=\frac{(base , rms , voltage) \sqrt {2}}{2\pi \times (base , frequency) }
$$

where current, voltage, and flux linkage are expressed respectively in volts, amperes, and volt-seconds.

For AC machines, the torque and speed can be also expressed in pu. The following base quantities are chosen:

* The base speed = synchronous speed
* The base torque = torque corresponding at base power and synchronous speed

$$
base ,torque=\frac{\text{base power (3 , phase) in VA})}{\text{base speed in radians/second} }
$$

Instead of specifying the rotor inertia in kg·m<sup>2</sup>, you would generally give the inertia constant H defined as

$$
H=\frac{\text{kinetic energy stored in the rotor at synchronous speed in joules}}{\text{base speed in radians/second}} \\\[8pt]
h=\frac{\frac{1}{2}\times J\omega ^2}{P\_{nom}}
$$

The inertia constant is expressed in seconds. For large machines, this constant is around 3 to 5 seconds. An inertia constant of 3 seconds means that the energy stored in the rotating part could supply the nominal load during 3 seconds. For small machines, H is lower. For example, for a 3 HP motor, it can be between 0.5 and 0.7 second.

## Examples

### Three-Phase Transformer

Consider, for example, a three-phase two-winding transformer. The following typical parameters could be provided by the manufacturer:

* Nominal power = 300 kVA total for three phases
* Nominal frequency = 60 Hz
* Winding 1: connected in wye, nominal voltage = 25 kV RMS line-to-line\
  resistance 0.01 pu, leakage reactance = 0.02 pu
* Winding 2: connected in delta, nominal voltage = 600 V RMS line-to-line\
  resistance 0.01 pu, leakage reactance = 0.02 pu
* Magnetizing losses at nominal voltage in % of nominal current: Resistive 1%, Inductive 1%

The base values for each single-phase transformer are first calculated:

* For winding 1:

{% columns fullWidth="true" %}
{% column %}
**Base power**

**Base voltage**

**Base current**

**Base impedance**

**Base resistance**

**Base inductance**
{% endcolumn %}

{% column %}
300 kVA/3 = 100e3 VA/phase

25 kV/sqrt(3) = 14434 V RMS

100e3/14434 = 6.928 A RMS

14434/6.928 = 2083 Ω

14434/6.928 = 2083 Ω

2083/(2π\*60)= 5.525 H
{% endcolumn %}
{% endcolumns %}

For winding 2:

{% columns fullWidth="true" %}
{% column %}
**Base power**

**Base voltage**

**Base current**

**Base impedance**

**Base resistance**

**Base inductance**
{% endcolumn %}

{% column %}
300 kVA/3 = 100e3 VA/phase

600 V RMS

100e3/600 = 166.7 A RMS

600/166.7 = 3.60 Ω

600/166.7 = 3.60 Ω

3.60/(2π\*60) = 0.009549 H
{% endcolumn %}
{% endcolumns %}

The values of the winding resistances and leakage inductances expressed in SI units are therefore

* For winding 1: R1= 0.01 \* 2083 = 20.83 Ω; L1= 0.02\*5.525 = 0.1105 H
* For winding 2: R2= 0.01 \* 3.60 = 0.0360 Ω; L2= 0.02\*0.009549 = 0.191 mH

For the magnetizing branch, magnetizing losses of 1% resistive and 1% inductive mean a magnetizing resistance Rm of 100 pu and a magnetizing inductance Lm of 100 pu. Therefore, the values expressed in SI units referred to winding 1 are

* Rm = 100\*2083 = 208.3 kΩ
* Lm = 100\*5.525 = 552.5 H

### Asynchronous Machine

Now consider the three-phase four-pole Asynchronous Machine block in SI units provided in the Machines library of Fundamental Blocks library. It is rated 3 HP, 220 V RMS line-to-line, 60 Hz.

The stator and rotor resistance and inductance referred to stator are

* Rs = 0.435 Ω; Ls = 2 mH
* Rr = 0.816 Ω; Lr = 2 mH

The mutual inductance is Lm = 69.31 mH. The rotor inertia is *J* = 0.089 kg.m<sup>2</sup>.

The base quantities for one phase are calculated as follows:

{% columns fullWidth="true" %}
{% column width="41.66666666666667%" %}
**Base power**

**Base voltage**

**Base current**

**Base impedance**

**Base resistance**

**Base inductance**

**Base speed**

**Base torque (3-phase)**
{% endcolumn %}

{% column width="58.33333333333333%" %}
3 HP\*746VA/3 = 746 VA/phase

220 V/sqrt(3) = 127.0 V RMS

746/127.0 = 5.874 A RMS

127.0/5.874 = 21.62 Ω

127.0/5.874 = 21.62 Ω

21.62/(2π\*60)= 0.05735 H = 57.35 mH

1800 rpm = 1800\*(2π)/60 = 188.5 radians/second

746\*3/188.5 = 11.87 newton-meters
{% endcolumn %}
{% endcolumns %}

Using the above base values, you can compute the values in per units.

Rs= 0.435 / 21.62 = 0.0201 pu Ls= 2 / 57.35 = 0.0349 pu

Rr= 0.816 / 21.62 = 0.0377 pu Lr= 2 / 57.35 = 0.0349 pu

Lm = 69.31/57.35 = 1.208 pu

The inertia is calculated from inertia *J*, synchronous speed, and nominal power.

$$
H = \frac{\tfrac{1}{2} , J , \omega^{2}}{P\_{\text{nom}}}
\= \frac{\tfrac{1}{2} \times 0.089 \times (188.5)^{2}}{3 \times 746}
\= 0.7065 \text{ seconds}
$$

If you open the dialog box of the Asynchronous Machine block in pu units provided in the Machines library of Fundamental Blocks (sps\_lib) library, you find that the parameters in pu are the ones calculated above.

## Base Values for Instantaneous Voltage and Current Waveforms

When displaying instantaneous voltage and current waveforms on graphs or oscilloscopes, you normally consider the peak value of the nominal sinusoidal voltage as 1 pu. In other words, the base values used for voltage and currents are the RMS values given above multiplied by $$\sqrt{2}$$.

## Why Use the Per-Unit System Instead of the Standard SI Units?

Here are the main reasons for using the per-unit system:

* When values are expressed in pu, the comparison of electrical quantities with their "normal" values is straightforward.

  For example, a transient voltage reaching a maximum of 1.42 pu indicates immediately that this voltage exceeds the nominal value by 42%.
* The values of impedances expressed in pu stay fairly constant whatever the power and voltage ratings.

  For example, for all transformers in the 3 kVA to 300 kVA power range, the leakage reactance varies approximately between 0.01 pu and 0.03 pu, whereas the winding resistances vary between 0.01 pu and 0.005 pu, whatever the nominal voltage. For transformers in the 300 kVA to 300 MVA range, the leakage reactance varies approximately between 0.03 pu and 0.12 pu, whereas the winding resistances vary between 0.005 pu and 0.002 pu.

  Similarly, for salient pole synchronous machines, the synchronous reactance *X*<sub>d</sub> is generally between 0.60 and 1.50 pu, whereas the subtransient reactance *X'*<sub>d</sub> is generally between 0.20 and 0.50 pu.

  It means that if you do not know the parameters for a 10 kVA transformer, you are not making a major error by assuming an average value of 0.02 pu for leakage reactances and 0.0075 pu for winding resistances.

The calculations using the per-unit system are simplified. When all impedances in a multivoltage power system are expressed on a common power base and on the nominal voltages of the different subnetworks, the total impedance in pu seen at one bus is obtained by simply adding all impedances in pu, without taking into consideration the transformer ratios.


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://www.opal-rt.com/docs/smart-power-simulation-software-sps/get-started/per-unit-system-of-units.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.