The V-model in systems engineering and where MIL, SIL and HIL sit on it
Simulation
11 / 22 / 2026

Key Takeaways
- The V-model pairs every design stage with a matching verification stage, which makes traceability natural and audits easier.
- MIL, SIL and HIL map to different levels of the V and let teams run right-side verification while the left side is still in progress.
- Continuous verification keeps the V’s rigour while matching the pace of electrification programs and software updates.
The V-model gives every requirement a matching test, and MIL, SIL and HIL are the tools that let you run those tests early enough for the answers to still change the design.
Late discovery is the expensive failure the V-model was built to prevent. Poor software quality cost the U.S. economy an estimated \$2.41 trillion in 2022, and a large part of that bill comes from defects found after integration, when every fix ripples through hardware, software and documentation at once.
Read as a sequence of handoffs, the V looks slow. Read as a map of what has to be proven at each level, it’s still the clearest structure for safety-critical embedded systems. For electrification teams, the useful question is how to verify each level continuously instead of waiting for the right side to arrive.
What the V-model means in systems engineering
The V-model is a development framework that pairs each design stage on the left side with a verification or validation stage on the right side. Requirements, architecture and detailed design descend the left arm, and unit, integration, system and acceptance testing climb the right arm to confirm each level was built correctly.
The shape is the point. Each horizontal pair links a decision to the evidence that proves it, so the system requirements written on day one define the system tests run months later. That pairing makes traceability natural and gives safety assessors a clear structure to audit, which is why automotive, aerospace and energy programs still organize their processes around it.
The stages on the left side of the V
The left side of the V moves from what the system must do to how each part will do it. Each stage refines the previous one and produces the specification that its matching test on the right side will later verify.
Most systems engineering V models use a version of these stages.
- Stakeholder and system requirements that define behaviour and constraints
- System architecture that allocates functions to hardware and software
- Software requirements derived from the allocated functions
- Software architecture and component design
- Detailed design and implementation of each unit
The quality of these stages determines how useful the right side can be. A vague requirement produces a vague test, and a test that can’t fail doesn’t prove anything.
How the right side of the V verifies each level
The right side of the V verifies each design level against its own specification. Unit tests check detailed design, integration tests check architecture, system tests check system requirements and acceptance tests confirm stakeholder needs, so a failure points directly at the level where the mistake was made.
In a classic program, the right side happens in that order and mostly after hardware exists. Simulation-based testing breaks that dependency. It lets teams run many right-side activities while the left side is still in progress, which is where MIL, SIL and HIL come in.
The table maps each V-model level to the verification method that usually covers it.
| V-model level | Typical verification method | What it proves |
| Detailed design and units | Model in the loop and unit testing | Control algorithms behave correctly against a plant model |
| Software components | Software in the loop | Generated or written code matches the validated model behaviour |
| Software and hardware integration | Hardware in the loop | Production code on the real controller works with real-time I/O and timing |
| System integration | Power hardware in the loop and system HIL | Several controllers and power stages work as one system |
| Acceptance | Vehicle, grid or site testing | The finished system meets stakeholder needs in its real setting |
Where model in the loop testing sits on the V
Model in the loop testing sits at the bottom of the V, alongside detailed design. Engineers test control models against plant models in simulation, so algorithms are verified before any code is written and design flaws are caught at the cheapest possible point.
MIL works best for exploring control concepts quickly. A team designing a battery charger controller can try three current regulation strategies in a day and keep the one that handles grid disturbances best, long before any of them touches a processor.
“A vague requirement produces a vague test, and a test that can’t fail doesn’t prove anything.”
Where software in the loop testing sits on the V
Software in the loop testing sits on the right side at the software component level. The actual production code, generated or hand written, runs on a computer against the same plant model used in MIL, so the team confirms that implementation didn’t change the validated behaviour.
SIL is fast and cheap to scale. Hundreds of test cases can run in parallel on servers, which makes it the natural home for regression suites that run on every code commit.
Where hardware in the loop testing sits on the V
Hardware in the loop testing sits at the integration level, where software meets the real controller. The production controller runs its final code while a real-time simulator emulates the plant through physical I/O, so timing, interrupts, analog conversion and communication buses are all tested as they will run in the product.
HIL is the first stage where real-time behaviour can fail. A control loop that worked perfectly in SIL can miss its deadline on the target processor or misread a sensor with an unexpected offset, and HIL exposes those issues without risking expensive hardware.
It’s also where fault testing becomes practical. Short circuits, sensor failures and grid faults can be injected safely and repeated hundreds of times. Engineers running OPAL-RT simulators commonly automate those campaigns overnight, so each software build is checked against the same fault library.
The cost of skipping this stage is well documented. Fixing a requirements error discovered in operations costs from 29 to more than 1,500 times as much as fixing it during requirements, according to a NASA study of project life cycle costs, which is why integration evidence gathered early pays for itself many times over.
How Automotive SPICE uses the V-model for software development
Automotive SPICE, often called ASPICE, uses the V-model as the structure of its process reference model for automotive software. Its engineering processes pair requirements, architecture and design activities with matching qualification and integration tests, and assessors check that each pair is consistent and traceable.
The ASPICE V model doesn’t prescribe tools, but it does expect evidence. Each software requirement needs a verification measure, each test result needs to trace back to the requirement it covers, and changes have to be managed so the evidence stays current. Simulation-based testing makes that evidence easier to produce, because automated MIL, SIL and HIL runs leave consistent, timestamped records.
For suppliers, the practical result is that test automation and traceability tooling are part of the assessment. A program that runs HIL tests by hand and records results in spreadsheets will struggle to show the consistency ASPICE expects.
“HIL is the first stage where real-time behaviour can fail.”
Why the classic V strains under electrification timelines
The classic V strains under electrification timelines because hardware, software and requirements all change faster than a single pass down and up the V can absorb. When a battery supplier changes cells or a grid code changes mid-program, a strictly sequential V sends the team back to the top.
Software-defined products make the strain permanent. Vehicles, chargers and grid controllers receive updates for years after launch, and each update has to be verified with the same rigour as the original release. A model that assumes one pass can’t carry that load.
The answer emerging across the industry keeps the V’s structure while speeding up its tempo. Requirements, design and tests stay paired, but verification runs continuously instead of waiting for the right side of the V to come around.
That’s the argument Simon Roy makes in The eVolution of testing, the Agile-V and continuous verification feature in Power in Mind Volume 12. He shows how teams keep the V’s rigour while running HIL and SIL on every change, so redesigns happen early instead of late.
How continuous verification reshapes the V without losing rigour
Continuous verification reshapes the V by running MIL, SIL and HIL tests automatically whenever requirements, models or code change. Each level of the V is verified many times during development, so the right side becomes a constant activity instead of a final phase, and the evidence stays current.
The rigour comes from automation and traceability. Every automated run ties results back to requirements, so an assessor can see not only that a test passed once but that it has kept passing as the design matured.
We see the strongest electrification teams treat the V as a living map instead of a schedule. With OPAL-RT real-time simulation running their HIL stages unattended, those teams keep every requirement verified from the first model to the last software update, and Power in Mind Volume 12 shows what that looks like in practice.

Automotive
11 / 26 / 2026
EV charger testing guide covering equipment, standards and HIL workflows
A guide to EV charger testing that covers EVSE test equipment, conformance testing for charging protocols and HIL workflows that tie them into one campaign.

Power Systems
11 / 25 / 2026
DNP3 protocol explained and how to test it in real time
An explainer on the DNP3 protocol in utility SCADA and a practical guide to testing DNP3 communication against a real-time model of the grid.

Automotive
11 / 20 / 2026
Motor controller and inverter testing with controller HIL
A practical guide to inverter testing and motor controller testing with controller HIL, from first commissioning steps to fault injection and power testing.
See how real-time simulation and hardware-in-the-loop (HIL) testing help aerospace engineers validate complex systems earlier in development.