Solid state transformer validation without building hardware first
Power Electronics
07 / 11 / 2026

Key Takeaways
- A solid state transformer replaces copper and iron with power electronic stages that add control, protection and DC output to the transformer.
- Modular medium voltage designs make SST converters hard to validate, with dozens of interacting cells and fast SiC switching.
- Real-time simulation proves SST control before medium voltage hardware is committed, protecting the schedule advantage that made SSTs attractive.
Solid state transformers replace copper and iron with power electronics, and the only practical way to prove their control, protection and grid behaviour before committing to medium voltage hardware is to validate them on a real-time model first.
Conventional transformers have become a serious constraint on new projects. Large power transformers can cost as much as \$10 million each, according to utilities surveyed by the U.S. Government Accountability Office, and lead times have stretched far enough that developers of data centres and DC grids are looking hard at power electronic alternatives.
A solid state transformer isn’t a drop-in replacement, though. It’s a multi-stage converter system with control loops, protection logic and fault behaviour that a passive transformer never had, and every one of those has to be proven before the unit carries a megawatt load.
What a solid state transformer replaces in the power chain
A solid state transformer replaces a line-frequency transformer with power electronic converters and a high frequency transformer. It steps voltage up or down, provides galvanic isolation and can also regulate voltage, correct power factor and offer a DC output, all within one controlled unit.
The high frequency link is what shrinks the hardware. Magnetic components get smaller as switching frequency rises, so an SST transformer operating at tens of kilohertz needs far less core material than a 60 Hz unit of the same rating.
The added control is what makes it attractive and what makes it demanding to validate. A conventional transformer simply passes faults and disturbances through, while a solid state transformer decides how to respond to each one in microseconds.
How an SST converter is built from power electronic stages
Most SST converters use three stages. A medium voltage rectifier converts grid AC to a DC link, an isolated DC-DC stage with a high frequency transformer steps the voltage down and an output stage produces low voltage AC or DC for the load.
Medium voltage operation usually requires modular designs. Because individual semiconductors can’t block the full medium voltage, the input stage is built from many cells in series, often in a cascaded H-bridge or modular multilevel arrangement, each with its own DC capacitor and isolated DC-DC converter.
That modularity adds control layers. The system has to balance capacitor voltages across dozens of cells, share power evenly through every isolated converter and keep the output stable while the input sees grid disturbances.
SiC devices are central to most current designs. Their low switching losses make high frequency isolation practical at medium voltage, but their fast edges put extra stress on insulation and on the timing of every control loop.
Why AI data centres are looking at solid state transformers
AI data centres are looking at solid state transformers because they need large blocks of power delivered quickly, more and more often at DC, and SSTs can convert medium voltage directly to a regulated DC bus. That removes conversion stages, saves floor space and gives operators more control over power quality.
The appeal for a solid state transformer data centre design comes down to a handful of practical gains.
- Fewer conversion steps between the utility feed and the server racks
- Smaller and lighter equipment for the same power rating
- Direct medium voltage to DC conversion for DC distribution designs
- Active control of voltage, harmonics and power factor at the feed
- Faster procurement than conventional large power transformers in many markets
“The added control is what makes it attractive and what makes it demanding to validate.”
What makes a power electronic transformer hard to validate
A power electronic transformer is hard to validate because its behaviour depends on many interacting control loops running across dozens of modules at high switching frequency. Faults inside one module, grid disturbances at the input and load steps at the output all have to be handled without tripping the whole unit.
Medium voltage prototypes are expensive and slow to build, and testing a fault on one can destroy it. That makes it tempting to defer difficult scenarios until late in the program, which is exactly when a control redesign is most costly.
The table summarizes the main validation challenges and how each is usually addressed.
| Validation challenge | Why it’s difficult | How it’s usually tested |
| Capacitor voltage balancing across cells | Dozens of cells interact through shared control and power flow | Controller HIL with every cell modelled individually |
| Isolated DC-DC power sharing | Small parameter differences cause uneven loading | Controller HIL with parameter spread across modules |
| Grid fault ride-through | Medium voltage faults are dangerous to stage on prototypes | Real-time grid model with the production controllers in the loop |
| Module failure and bypass | A failed cell has to be isolated without tripping the unit | Fault injection on the simulated converter |
| Thermal and insulation limits | Fast SiC edges stress materials in ways models can’t fully capture | Power hardware testing on reduced-scale modules |
“None of them has to accept a first-of-a-kind unit on faith.”
How real-time simulation tests an SST before hardware exists
Real-time simulation tests an SST by running a detailed model of every converter stage, the high frequency transformer and the grid on FPGA hardware, while the real control boards operate it. The controllers see the same signals they’d see in the finished unit and respond in real time.
That arrangement lets the team run grid faults, module failures and load steps hundreds of times without any medium voltage equipment. Engineers using OPAL-RT simulators commonly model each cell separately, so capacitor balancing and module bypass logic are tested exactly as they’ll run in production.
Schedules are where this pays off most. Large power transformer lead times are now commonly quoted at 36 months and can reach 60, according to the U.S. Department of Energy, so an SST program that proves its control early can turn a procurement advantage into a delivery advantage instead of losing it to late redesigns.
Moving from controller tests to medium voltage hardware
Move to medium voltage hardware once the control firmware has passed its full scenario library on the real-time model. Hardware testing can then focus on what models can’t show, including insulation, thermal behaviour and electromagnetic interference, instead of debugging control logic on expensive prototypes.
Reduced-scale power hardware tests often bridge the gap. A few physical modules run at real power while the rest of the converter stays simulated, which checks the hardware against the model without building the full unit. Any mismatch feeds back into the model, so later full-scale tests start from a model that’s already been corrected against real modules.
What early SST validation means for project schedules
Early SST validation means the control and protection design is settled before medium voltage hardware is committed, so the hardware phase confirms the design instead of discovering it. That keeps a solid state transformer program on the schedule that made it attractive in the first place.
That matters for every party in the project. The developer gets predictable delivery, the utility gets evidence of grid behaviour and the operator gets equipment that has been tested against the conditions it will actually see. None of them has to accept a first-of-a-kind unit on faith.
We’ve seen SST teams avoid whole prototype iterations by treating the real-time model as the first unit they build. With OPAL-RT real-time simulation in that role, the converter they finally energize has already handled every fault on the list many times over.

Power Systems
11 / 13 / 2026
Grid forming inverters, how they work and how to test them
A technical explainer on how grid forming inverters and their control loops work, and how to test grid forming control through faults, islanding and weak grids.

Automotive
11 / 08 / 2026
Active vs passive cell balancing and how to validate balancing logic before pack build
A comparison of active and passive cell balancing in battery packs and a practical guide to validating balancing logic on HIL before pack build.

Power Systems
11 / 03 / 2026
Medium voltage and grid interactive UPS systems for data centers
An engineering guide to medium voltage and grid interactive UPS systems for data centres, covering static transfer switches, modular designs and pre-commissioning validation.